Availability?
Last year, we did major dock replacement. Started in May, expected to finish in June but the supplier ran out of the Trex we were using. A little bit trickled in over the summer, but not enough to justify sending a crew and equipment for a day's work and then moving to another location repeatedly. Finally finished in the fall. I don't know if Covid will continue to slow production, but I suggest you buy ALL needed materials up front instead of a little bit at a time as work and budget progress. At the same time, be aware of security if you're not constantly on site, as materials that sit alone tend to disappear.
|