The CT PPA for Millstone was above the market rate when entered into... it ends in 2029.

The VT PPA for Seabrook (NextEra... I have stock) goes until 2035(?).

It doesn't appear that any of the other sites with significant transmission infrastructure is being looked at... though I believe the technology exists.