Noon Thursday everything was done. The crane is being disassembled by a small crew. The only thing left is to throw the big switch connected to the Grid.

The new turbine is now privately owned, leasing the land it sits on from the town. The turbine owners will charge the Town 15.5 cents per KWh for the power it makes for the next 25 years. The rest of us pay 10 cents. NB