As has already been explained, as of this Friday June 8th, construction will cease and all will be restored to the previous flow of traffic, including the option of turning left from both lanes coming to the light from Hannafords.

This information comes from Mr. Sperry, who is is the New Hampshire Department of Transportation’s on-site contract administrator AND from engineering plans available online.

The summer traffic pattern will be pretty much the same as last summer, except perhaps for the new crosswalk location.

AFTER Labor Day, construction will start again and, I assume, be completed before winter.

Once the construction is finished, the traffic pattern will not be much different than it was except for the crosswalk.

Why not do it all after Labor Day? Not enough time. So some was done in the spring and some after Labor Day.