I was asked in another thread for a progress report. I thought it best to answer it here.

I have ordered and paid for the still. It’s scheduled to be delivered on September 21. There is another key piece of equipment that is scheduled to be delivered sometime in the next 24 hours.

When I received the variance from the city I stated I was a year to a year and a half away. I am currently way ahead of schedule however I am not ready to change any target dates. I have red tape in front of me and have no idea how long that’ll take to deal with.