Originally Posted by DRH
Your town's Conservation Commission then reviews the application, approves it, and the Town Clerk then distributes the remaining copies. After 25 days from the filing date, the repairs may begin unless the applicant receives notification to the contrary from the DES. I believe the permit to make repairs is then valid for five years.
Actually, The waiting period is only 10 calendar days, if the PBN Form contains a waiver of intervention (signature) from the Conservation Commission.

I've done two PBNs in the last 10 months. It's really no big deal. The permit does ask for things like USGS topographic and tax maps but those are easy to find online.