Default Permit

I just finished a DES permit for minimal changes. I won't sugar coat it, the permit is time consuming. It took my wife and I several hours to complete as there are portions you have to send to the DHR (NH Division of Historical Resources), maps and plans you need to create, and in our case four copies needed to be submitted to the town (Alton) conservation commission for their consideration. After the town approves it (hopefully) we then send the final copy to Concord for approval.

Let me note that we are removing a manmade object (old crib dock) from the lake, NOT building anything new. Good Luck